Regeneration Tue, Mar 22, 2016 5:35 PM
Balfour Beatty, the international infrastructure group, announces today its joint venture with Cavendish Nuclear has received instruction for the third phase of a contract to construct a new silo maintenance facility for Sellafield Ltd, valued at £160 million.
Working in a 45:55 joint venture, Balfour Beatty and Cavendish Nuclear (the UK’s largest supplier of specialist services to the nuclear industry) will deliver the facility which will be an integral part of Sellafield’s long-term waste retrieval hazard reduction programme.
This final phase of works follows the first two phases consisting of a £5.5 million preliminary design phase and £12.5 million detailed design and enabling works.
The new mechanical handling plant will support two existing waste silos with retrieving historic waste and reducing hazard. At the heart of the heavily reinforced concrete structure, which has a footprint of 0.5 hectares and will be 25 metres high, robotic installations will enable the Sellafield team to operate in a safe and controlled environment.
Balfour Beatty is bringing together its broad range of expertise to deliver the project including design, procurement, civil engineering, construction and mechanical and electrical capabilities. In addition, the company will provide fully integrated commissioning and pre-operations delivery strategy and will train Sellafield’s employees in operating the facility.
A team of more than 100 engineers including nuclear specialists, civil and structural engineers and architectural technicians is currently using Building Information Modelling to create a full 4D design specification that dramatically reduces the construction programme. Work is scheduled to complete in autumn 2017, and the project will employ over 300 people at the height of construction.
Balfour Beatty Executive Chairman, Steve Marshall said: “The UK infrastructure market includes significant opportunities for nuclear decommissioning and clean-up activities. Similarly, new nuclear build and the construction of new power generation projects will bring us an opportunity to deploy our extensive experience.
“Balfour Beatty has a strong heritage in the nuclear sector including our work across the existing fleet of UK nuclear power stations and our 35 year presence at Sellafield. We look forward to working with Cavendish Nuclear to deliver a facility that will support Sellafield Limited’s overall waste retrieval and hazard reduction programme."
Featured News
Fire resistant glazing and fire-rated glass door-sets manufactured by Promat UK have...
Fassa UK is excited to introduce our exceptional range of self-levelling screeds, now...
BUILDING PRODUCT LIBRARY - LATEST BROCHURES
Your high performanc...
By James Hardie
James Hardie brings...
By James Hardie
fermacell® The Speci...
By James Hardie
Hardie backer fibre...
By James Hardie
RIVERSTONE® - DISCOV...
By SSQ
BUILDING PRODUCT DIRECTORY - LATEST PRODUCTS
Senses Kitchen Surfaces. Beautifully Crafted, Effortlessly Maintained. The Senses range of...
FASSA's new SM 485: Your choice for a fast-setting, self-levelling smooth coat for interior floors,...
FASSA's new SL 416: A fast-setting, self-levelling smooth coat for interior floors. With superb...
CONSTRUCTION VIDEOS - LATEST VIDEOS
Specification Insights with Majestic London Showers
“Building with stone wool insulated sandwich panels” written by Professor Imperadori, is now...
Portakabin | Installation at the iconic Admiralty Arch, London