Digital construction technology helping to create new stadium

Latest News Mon, Sep 26, 2022 6:24 AM

Workers at Laing O’Rourke are confident that Everton Stadium will have the ‘wow’ factor – because they have already built it once.

Craig Wallace, a Digital Engineer for Laing O’Rourke, is one of a select few with the responsibility for ensuring the project’s approach towards ‘digital’ uses leading processes, technology and data.

One of the ways this is evident is through a process known as Building Information Modelling (BIM), which has provided Laing with the opportunity to build the project twice – virtually, and now in reality.

As such, the 52,888-seater stadium has already been completed in digital form, in mind-boggling and minute detail, from the millimetre-accurate assembly of steelwork, prefabricated concrete walls and giant roof trusses, through to pinpoint positioning of wiring, plumbing, light switches and plug sockets.

“We like to think we have already built Everton Stadium,” explained Craig, who works within the offices at Bramley-Moore Dock.

“It’s been built virtually on screen in a simulated environment, and now physically on site.

“The real benefit is that this enables us to resolve issues upfront, in a simulated environment, before work begins on-site.

“That promotes efficiency gains, reduction in risks, leads to programme and cost benefits and provides certainty throughout the life-cycle of the build.

“It took some teamwork to pull together and it’s a real collaborative effort, in that our entire supply chain contribute to the model.

“All of the different disciplines, such as electrical, mechanical, structural and architectural, develop their own 3D model, involving their scope of work, and then share them with us on a collaborative online platform.

“That provides us with around 1,500 shared model files, which we then combine into a master model for the entire team to use.

“From that, the entire project team can work to co-ordinate the build and ensure there are no clashes within the disciplines.”

The 3D model, representing what will be constructed in terms of the design, incorporates the three dimensions of width, depth and height.

Then, by introducing the vital dimension of time and linking model elements to the construction programme activities, the cutting-edge 4D model allows the Laing O’Rourke team to visualise the construction sequence and assess potential risks or clashes in the programme, along with opportunities that might not have been seen using more traditional methods.

“What you might see in the industry is the model being linked to the programme and that shows the sequencing of the build,” explained Craig.

“In addition to this, we focus on including elements such as coordinating mobile cranes, storage zones, engineering controls, walking routes and more.

“That really helps to drive what we do on site and how we can coordinate different pieces of work safely. This is our highest value.”

The rolling model can be accessed by the workforce on site, via screens or mobile phones, enabling them to undertake the precise workloads and feedback on progress to keep the information flow going.

“Working with our supply chain, we can use the model and embedded data to visually track the progress of the build and then communicate this through dashboard reporting,” added Craig.

“The model is integral to dictating, with precise detail, the just-in-time delivery slots for tonnes of steelwork and the thousands of concrete wall panels, pillars and beams.

“The model is accurate as it can be, and by coordinating the disciplines we can then increase the accuracy as the design progresses.

“Out of the models we can then extract the drawings and then they, along with the 3D models, can be used in parallel by the workforce.”

Featured News

Specification news
Eyrise glass transforms Grade II-listed London...

Eyrise dynamic solar shading glass has transformed a Grade II-listed London...

Read More >>

Specification news
Pendock metal pipe boxing conceals high-rise utilities...

Metal pipe boxing from the Pendock Profiles range has been installed in the communal...

Read More >>

BUILDING PRODUCT LIBRARY - LATEST BROCHURES

Novantica - Cement Free Restoration  Brochure

Novantica - Cement F...
By Fassa Bortolo

Download Now >>

Fassatherm System - Product Catalogue  Brochure

Fassatherm System -...
By Fassa Bortolo

Download Now >>

Fassarend System - Product Catalogue  Brochure

Fassarend System - P...
By Fassa Bortolo

Download Now >>

Fassalime System - Product Catalogue  Brochure

Fassalime System - P...
By Fassa Bortolo

Download Now >>

Sport England’s Performance Archery Centre Brochure

Sport England’s Perf...
By Passivent

Download Now >>

BUILDING PRODUCT DIRECTORY - LATEST PRODUCTS

Straightcurve®
Straightcurve®

Straightcurve® – headquartered in Australia, is renowned for high-end innovative garden edging,...

Read More >>

RLG600 Access Flooring System
RLG600 Access Flooring System

The Kingspan RLG600 raised access floor panel is intended for light office use and is capable of...

Read More >>

RHG600 Simploc
RHG600 Simploc

Kingspan RHG600 Simploc is the heavy grade floor system, capable of handling up to a 12kN/m2...

Read More >>

CONSTRUCTION VIDEOS - LATEST VIDEOS

Discover the first-ever reference book for stone wool insulated sandwich panels
Discover the first-ever reference book for stone wool insulated sandwich panels

“Building with stone wool insulated sandwich panels” written by Professor Imperadori, is now...

Watch Now >>

Portakabin | Installation at the iconic Admiralty Arch, London
Portakabin | Installation at the iconic Admiralty Arch, London

Portakabin | Installation at the iconic Admiralty Arch, London

Watch Now >>