Influential committee of MPs criticise stop-start approach of Government on major projects

Latest News Fri, Oct 6, 2023 6:08 AM

The fall-out from the Prime Minister’s decision to scrap the Birmingham to Manchester route of HS2 continues to hit the Government.

The decision has already been roundly criticised, now the chair of the Public Accounts Committee has questioned whether this week’s confirmation undermines confidence in the Government to make decisions and keep control of major projects.

Dame Meg Hillier MP, Chair of the Public Accounts Committee, said: "Stop-start approaches on large and complex infrastructure projects plainly do not represent value for money for the taxpayer. And this approach undermines wider confidence that government programmes for major infrastructure investment will be delivered. In a globally competitive world companies may now choose to invest their time and skills in other countries.

"The original plans for HS2 were calculated on the basis of the line extending beyond Birmingham - both the cost to the taxpayer of construction, and the boost to local economic development.

"As a Committee we have been raising concerns about HS2 for a full decade, so this latest change is little surprise. It has been confirmed that HS2 will run to London Euston, but it was only in July that we warned that Government does not know what it is trying to achieve with the planned new station there, and we had raised concerns about the considerable cost of the two-year pause which had been presented by Government as a money-saving move.

"Our HS2 Euston report highlighted that the costs of such major course-changes are not that simple. We will continue to closely scrutinise the delivery of HS2, and it is likely we will be examining the costs of this latest decision in the months to come."

Meanwhile, Shevaun Haviland, Director General of the BCC, said businesses had remained hopeful the Prime Minister would listen to their calls to push on and deliver the long-term infrastructure this country needs: “This is disappointing news for them and our economy as cancelling the second phase of HS2 will massively impact the country’s rail network.

“Without this vital additional capacity, any plans to improve the UK’s freight and passenger services will be restricted.

“We will be left with a rail system unable to effectively connect all our regional economies.

“Each train, that HS2’s capacity would have unlocked, had the potential to remove up to 129 lorries from the road, this will also be a lost opportunity to build a low-carbon freight transport system.

“And it will affect our global trade: one in four sea containers arriving or departing from a port is carried by rail, and additional capacity is urgently needed. When we talk about growth, we mean trade. Our global partners must trust that we can move not only at speed but with capacity.

“Businesses and regional governments will now be scratching their heads as they work out how to fill the hole left in their strategic plans by the loss of HS2’s further phases. 

“Government must quickly set out the detail of its new plans, especially around timescales and the release of funds for the new projects it has put forward today.

“It must also urgently revisit the functioning of our planning system, as so much of the delay and cost around HS2 has come from its inability to cope with a large-scale infrastructure project. Let’s learn the lessons from HS2; let’s make sure these new promises are deliverable before we spend another penny of taxpayers’ money.”

Featured News

Specification news
Optimism slightly weakens but architects still...

In June, architects remained positive about their workloads over the next three...

Read More >>

Specification news
Enhanced carbon database revealed after government...

Major changes to the Built Environment Carbon Database (BECD) have been revealed...

Read More >>

BUILDING PRODUCT LIBRARY - LATEST BROCHURES

Reynaers RIBA CPD Seminars Brochure

Reynaers RIBA CPD Se...
By Reynaers Aluminium L...

Download Now >>

General Care & Maintenance Brochure Brochure

General Care & Maint...
By Reynaers Aluminium L...

Download Now >>

A New Era Of Energy Efficient Buildings Brochure

A New Era Of Energy...
By Reynaers Aluminium L...

Download Now >>

Colorcoat HPS200 Ultra super durable case studies Brochure

Colorcoat HPS200 Ult...
By Tata Steel

Download Now >>

Confidex® Guarantee datasheet Brochure

Confidex® Guarantee...
By Tata Steel

Download Now >>

BUILDING PRODUCT DIRECTORY - LATEST PRODUCTS

ParallelRoof 100
ParallelRoof 100

ParallelRoof 100 is a non-insulated conservatory system that provides the perfect solution for any...

Read More >>

MasterLine 8 Heritage Window and Door System
MasterLine 8 Heritage Window and Door System

MasterLine 8 is a high-specification, next-generation window and door system that delivers...

Read More >>

ConceptSystem 77 Heritage Window and Door System
ConceptSystem 77 Heritage Window and Door System

The ConceptSystem 77 system incorporates a comprehensive range of inward- and outward-opening window...

Read More >>

CONSTRUCTION VIDEOS - LATEST VIDEOS

Mira Vista Heatloop
Mira Vista Heatloop

Mira Showers is delighted to introduce the new Mira Vista HeatloopTM – an innovative and stylish...

Watch Now >>

Why our Canopies Last Longer
Why our Canopies Last Longer

https://www.aandslandscape.co.uk/ Find out why A&S Landscape Canopies last longer than alternatives....

Watch Now >>

Enclosed Dining Canopy - Hampton Gardens School
Enclosed Dining Canopy - Hampton Gardens School

A&S Landscape designed and installed a large enclosed, curved roof canopy for Hampton Gardens School...

Watch Now >>