HS2 now very poor value for money, say MPs

Latest News Wed, Feb 7, 2024 7:38 AM

The High Speed 2 (HS2) programme, after the cancellation of its latter stages to run only from London to the West Midlands (Phase 1), will offer very poor value for money for the taxpayer.

In a new report, the Public Accounts Committee (PAC) offers its verdict on both the high-speed rail programme and Euston station. The PAC’s report is the latest addition to over a decade of scrutiny raising concerns around the management of HS2.

The Government has accepted that delivering only Phase 1 will not be value for money, as its total costs significantly outweigh its benefits. The Department for Transport (DfT) told the PAC it was still better to complete Phase 1 – a calculation made by excluding the £23bn spent to date, and including as a benefit of the project avoiding approximately £11bn of remediation costs from cancelling entirely. The PAC has been left with little assurance over the calculations, and calls for a clear summation of Phase 1’s benefits.

The report raises questions as to the many as-yet unknown ramifications of the decision to cancel HS2’s Northern leg. These range from how land and property now no longer needed will be disposed of, taking into account the needs of the taxpayer, local interests and fairness to those who have had their properties compulsorily purchased; impacts on other rail projects dependent on the cancelled phases; what will be delivered with a redirected £36bn** and when; down to how the high-speed trains (which will likely run slower than existing trains on tracks not designed for their speed) will operate as part of the network.

As repeatedly highlighted by the PAC, cost overruns and delays have been a constant problem throughout the whole HS2 project. The estimated cost of the completion of Phase 1 with inflation range as high as £67bn**. Poor cost management indicates a failure of governance and oversight at both HS2 Ltd and DfT, and the report calls for answers within six months as to how these issues will now be brought under acceptable and properly accountable control.

The report warns there are also urgent decisions to be made on funding the development of HS2 Euston, which is dependent on attracting private finance to pay for it. The Government has no plan yet on how to make this happen, and the PAC is highly sceptical that investment can be attracted of the scale and speed required to make Euston a success.

Dame Meg Hillier MP, Chair of the Committee, said: “The decision to cancel HS2’s Northern leg was a watershed moment that raises urgent and unanswered questions, laid out in our report. What happens now to the Phase 2 land, some of which has been compulsorily purchased? Can we seriously be actively working towards a situation where our high-speed trains are forced to run slower than existing ones when they hit older track? Most importantly, how can the Government now ensure that HS2 deliver the best possible value for the taxpayer?

“HS2 is the biggest ticket item by value on the Government’s books for infrastructure projects. As such, it was crying out for a steady hand at the tiller from the start. But, here we are after over a decade of our warnings on HS2’s management and spiralling costs – locked into the costly completion of a curtailed rump of a project with many unanswered questions and risks still attached to delivery of even this curtailed project.”

Featured News

Specification news
NFRC roofing industry survey suggests a positive...

The latest NFRC State of the UK Roofing Industry survey, covering the second quarter...

Read More >>

Specification news
Barking Riverside is growing to 20,000 homes,...

BRL has submitted a new Outline Planning Application that could see up to 20,000 new...

Read More >>

BUILDING PRODUCT LIBRARY - LATEST BROCHURES

Novantica - Cement Free Restoration  Brochure

Novantica - Cement F...
By Fassa Bortolo

Download Now >>

Fassatherm System - Product Catalogue  Brochure

Fassatherm System -...
By Fassa Bortolo

Download Now >>

Fassarend System - Product Catalogue  Brochure

Fassarend System - P...
By Fassa Bortolo

Download Now >>

Fassalime System - Product Catalogue  Brochure

Fassalime System - P...
By Fassa Bortolo

Download Now >>

Sport England’s Performance Archery Centre Brochure

Sport England’s Perf...
By Passivent

Download Now >>

BUILDING PRODUCT DIRECTORY - LATEST PRODUCTS

Straightcurve®
Straightcurve®

Straightcurve® – headquartered in Australia, is renowned for high-end innovative garden edging,...

Read More >>

RLG600 Access Flooring System
RLG600 Access Flooring System

The Kingspan RLG600 raised access floor panel is intended for light office use and is capable of...

Read More >>

RHG600 Simploc
RHG600 Simploc

Kingspan RHG600 Simploc is the heavy grade floor system, capable of handling up to a 12kN/m2...

Read More >>

CONSTRUCTION VIDEOS - LATEST VIDEOS

Discover the first-ever reference book for stone wool insulated sandwich panels
Discover the first-ever reference book for stone wool insulated sandwich panels

“Building with stone wool insulated sandwich panels” written by Professor Imperadori, is now...

Watch Now >>

Portakabin | Installation at the iconic Admiralty Arch, London
Portakabin | Installation at the iconic Admiralty Arch, London

Portakabin | Installation at the iconic Admiralty Arch, London

Watch Now >>