HS2 now very poor value for money, say MPs

Latest News Wed, Feb 7, 2024 7:38 AM

The High Speed 2 (HS2) programme, after the cancellation of its latter stages to run only from London to the West Midlands (Phase 1), will offer very poor value for money for the taxpayer.

In a new report, the Public Accounts Committee (PAC) offers its verdict on both the high-speed rail programme and Euston station. The PAC’s report is the latest addition to over a decade of scrutiny raising concerns around the management of HS2.

The Government has accepted that delivering only Phase 1 will not be value for money, as its total costs significantly outweigh its benefits. The Department for Transport (DfT) told the PAC it was still better to complete Phase 1 – a calculation made by excluding the £23bn spent to date, and including as a benefit of the project avoiding approximately £11bn of remediation costs from cancelling entirely. The PAC has been left with little assurance over the calculations, and calls for a clear summation of Phase 1’s benefits.

The report raises questions as to the many as-yet unknown ramifications of the decision to cancel HS2’s Northern leg. These range from how land and property now no longer needed will be disposed of, taking into account the needs of the taxpayer, local interests and fairness to those who have had their properties compulsorily purchased; impacts on other rail projects dependent on the cancelled phases; what will be delivered with a redirected £36bn** and when; down to how the high-speed trains (which will likely run slower than existing trains on tracks not designed for their speed) will operate as part of the network.

As repeatedly highlighted by the PAC, cost overruns and delays have been a constant problem throughout the whole HS2 project. The estimated cost of the completion of Phase 1 with inflation range as high as £67bn**. Poor cost management indicates a failure of governance and oversight at both HS2 Ltd and DfT, and the report calls for answers within six months as to how these issues will now be brought under acceptable and properly accountable control.

The report warns there are also urgent decisions to be made on funding the development of HS2 Euston, which is dependent on attracting private finance to pay for it. The Government has no plan yet on how to make this happen, and the PAC is highly sceptical that investment can be attracted of the scale and speed required to make Euston a success.

Dame Meg Hillier MP, Chair of the Committee, said: “The decision to cancel HS2’s Northern leg was a watershed moment that raises urgent and unanswered questions, laid out in our report. What happens now to the Phase 2 land, some of which has been compulsorily purchased? Can we seriously be actively working towards a situation where our high-speed trains are forced to run slower than existing ones when they hit older track? Most importantly, how can the Government now ensure that HS2 deliver the best possible value for the taxpayer?

“HS2 is the biggest ticket item by value on the Government’s books for infrastructure projects. As such, it was crying out for a steady hand at the tiller from the start. But, here we are after over a decade of our warnings on HS2’s management and spiralling costs – locked into the costly completion of a curtailed rump of a project with many unanswered questions and risks still attached to delivery of even this curtailed project.”

Featured News

Specification news
Gleeds to lead regeneration of Trent Sports District

International property and construction consultancy Gleeds has been appointed as lead...

Read More >>

Specification news
Hotel & leisure opportunities improve as chains invest

Opportunities for work in the hotel & leisure sector are improving as chain hotels...

Read More >>

BUILDING PRODUCT LIBRARY - LATEST BROCHURES

Paints & Coatings Brochure

Paints & Coatings
By F.H. Brundle

Download Now >>

Cedral Roofs Brochure Brochure

Cedral Roofs Brochur...
By Cedral by Etex

Download Now >>

Cedral Facades Brochure Brochure

Cedral Facades Broch...
By Cedral by Etex

Download Now >>

2026 Product Brochure Brochure

2026 Product Brochur...
By ​The Radiator Compan...

Download Now >>

System for Laying Floor and Wall Coverings Brochure

System for Laying Fl...
By FassaFloor

Download Now >>

BUILDING PRODUCT DIRECTORY - LATEST PRODUCTS

Aluminium Framing System
Aluminium Framing System

Benefits: Decking and BeyondThe benefits of aluminium framing systems: Why Outdure® Qwickbuild®...

Read More >>

Aluminium Fencing
Aluminium Fencing

When it comes to securing your property while enhancing its aesthetic appeal, few fencing solutions...

Read More >>

Adjustable Pedestals & Paving Supports
Adjustable Pedestals & Paving Supports

The smarter, faster way to lay perfectly level decking, paving, and flooring on any surface.Whether...

Read More >>

CONSTRUCTION VIDEOS - LATEST VIDEOS

Fortitude™ Steel Railing Systems: Adjustable Off-the-Shelf Balustrade Guide
Fortitude™ Steel Railing Systems: Adjustable Off-the-Shelf Balustrade Guide

Fortitude Steel Railings and Balustrades are one of the most versatile, off-the-shelf, steel...

Watch Now >>

Pro-Railing® Stainless Steel Handrail Systems: 6 Modern Balustrade & Glass Railing Solutions
Pro-Railing® Stainless Steel Handrail Systems: 6 Modern Balustrade & Glass Railing Solutions

Pro-Railing® – our Stainless Steel Handrail Component System with six stunning ranges to choose...

Watch Now >>

Why Professionals Choose Outdure QwickBuild | Aluminium Deck Frame Case Study
Why Professionals Choose Outdure QwickBuild | Aluminium Deck Frame Case Study

This case study explores a stunning designer terrace featuring the Outdure QwickBuild system,...

Watch Now >>