Huge HS2 bridge move completed four days ahead of schedule

Latest News Wed, Aug 27, 2025 10:49 AM

A specialist HS2 engineering team has moved a 112m long, 1,631 tonne steel structure over a section of Lawley Middleway – part of Birmingham’s ring road, four days ahead of schedule.

The operation was successfully delivered by HS2’s main works contractor in the West Midlands, Balfour Beatty VINCI (BBV) and their bridge move contractor Mammoet.

To minimise disruption to road users, the huge span was moved during night-time road closures - moving between 18 and 24 metres every night using a special skidding system - ensuring that the road has remained open during the day.

From the first day of the move on 15 August, the team - helped by favourable weather conditions, were able to get ahead of programme, meaning the road will be back to normal from 6am on Friday 22 August instead of the planned full reopening on Monday 25 August.

HS2’s Head of Delivery for the Curzon Approaches, Greg Sugden said: “This is a fantastic achievement for the team, and the culmination of two years’ work including detailed design, planning, construction and delivery of this highly technical launch operation.

“It is the first steel structure to be put in place for the one mile stretch of viaducts on the approach to Birmingham Curzon Street Station – a pivotal part of the high-speed railway now starting to take shape.”

Georgios Markakis, Project Manager at Balfour Beatty VINCI said: “This is a proud moment for my team, who have worked hard to deliver this impressive feat of engineering. Through careful planning and expert support from our supply chain, we were able to deliver the operation much quicker than planned.

“Not only have we successfully delivered a milestone feat of engineering on the HS2 project, we’ve also been able to get the road back to normal early – which is good news for everyone.”

Rather than building the bridge in situ, disruption to road users was drastically reduced by constructing the steel span on land next to Digbeth Canal over the last two years. On 15 August 2025, heavy lifting engineering experts Mammoet rotated the bridge 90 degrees using two self-propelled modular transporters (SPMTs).

Over the following four nights, a skidding system - with a jacking push/pull mechanism, was used alongside the SPMTs to move the structure into place across Lawley Middleway. This combination of techniques is rarely used and is a first for BBV on the HS2 project.

Lawley Middleway bridge forms part of the railway’s approach to Birmingham, with high-speed trains travelling out of the west portal of the 3.5 mile Bromford Tunnel at Washwood Heath and onto a one mile stretch of five connected viaducts - Duddeston Junction, Curzon 1, Curzon 2, Lawley Middleway and Curzon 3 which links onto the platforms of Birmingham Curzon Street Station.

Now at peak productivity, work will progress on this section of the railway with the second Bromford Tunnel breakthrough, Curzon 2 viaduct move, first Duddeston Junction Viaduct move, reopening of Aston Church Road, demolition of the old Aston Church Road bridge and start of construction of the new Saltley Viaduct – all set to happen over the next 12 months.

Featured News

Specification news
New towns will need Government leadership and funding,...

The Built Environment Committee has published its report, ‘New Towns: Laying the...

Read More >>

Specification news
CIBSE announces dedicated resource for the domestic...

CIBSE is pleased to announce that the Domestic Building Services Panel (DBSP) has now...

Read More >>

BUILDING PRODUCT LIBRARY - LATEST BROCHURES

Our product range at a glance... Brochure

Our product range at...
By Premier Loft Ladders...

Download Now >>

Your Specialist Partner in Composite Steel Roof & Floor Decking Brochure

Your Specialist Part...
By RMD Profiles Ltd

Download Now >>

PVC-U System Fully Reversible Windows by Epwin Window Systems Brochure

PVC-U System Fully R...
By Epwin window systems...

Download Now >>

Spectus Bevelled Windows and Doors Brochure

Spectus Bevelled Win...
By Epwin window systems...

Download Now >>

BUILDING PRODUCT DIRECTORY - LATEST PRODUCTS

Supreme Heavy-Duty Loft Ladder
Supreme Heavy-Duty Loft Ladder

The Supreme heavy-duty loft ladder is supplied as a ready to fit unit. It is manufactured from high...

Read More >>

Designo Loft Ladder
Designo Loft Ladder

The Elite heavy-duty loft ladder...The Elite heavy duty concertina loft ladder is supplied without a...

Read More >>

Elite Loft Ladder
Elite Loft Ladder

The Elite heavy-duty loft ladder...The Elite heavy duty concertina loft ladder is supplied without a...

Read More >>

CONSTRUCTION VIDEOS - LATEST VIDEOS

Proctor Air® Product Explainer
Proctor Air® Product Explainer

Proctor Air® is an air and vapour permeable, highly water resistant roofing underlay. Its...

Watch Now >>

Discover the Power of Blue Roofs in Urban Flood Management
Discover the Power of Blue Roofs in Urban Flood Management

In this video, we explore how blue roofs are transforming urban landscapes by helping to mitigate...

Watch Now >>

RMD Profiles - UK Experts in Metal Decking, Design Installation
RMD Profiles - UK Experts in Metal Decking, Design Installation

At RMD Profiles, we’re more than just metal decking. From supply-only solutions to full design and...

Watch Now >>