Hotel, Sport & Leisure Wed, Mar 23, 2016 9:11 AM
Leading UK construction firm Barr Construction took a big stride forward with the Ashton Gate rebuild successfully lifting the 106m Dolman Stand roof truss into place.
Weighing 75 tonnes, the roof extension was built at ground level over the past few weeks before two 200 tonnes cranes were used to lift the steel truss into place.
The lifting of the roof truss is one of the most complicated part of the £45 million rebuild of Bristol City and Bristol Rugby’s ground to-date.
Mike Henderson, operations manager for Barr Construction said: “Today has been a landmark event. The design has had to take in a lot of difficult parameters. From working with the existing Dolman roof to the new South Stand, we’ve had to work to tight tolerances of 10mm at each end of the truss.
“When you consider that it is 106 metres long and weighs 75 tonnes it’s not an easy piece of steel to slot in to place, but it was a momentous occasion to see that it has today.”
Bristol Sport chairman, Martin Griffiths said: “It’s been a big week for the stadium. Last Wednesday we saw the gap close in the South Stand and seating being fitted, today the lift of the Dolman roof truss. It was quite an incredible feat of engineering to see it slot seamlessly into place.
“Fans coming to this weekend’s games at Ashton Gate will really start to get a sense of what this stadium is going to become.”
Barr construction has been on site since July last year. Phase One consisted of the demolition and rebuild of the South Stand with Phase Two seeing the Dolman Stand remodelled to include an extended roof and new lower tier.
Phase Three will start this summer and see the Williams stand demolished and replaced with a two-tier stand that will hold 11,000 people.
Featured News
The International Day of Disabled People (IDDP) occurs annually on December 3rd has...
Gerflor and Gradus is excited to announce the expansion of their renowned Hospitality...
BUILDING PRODUCT LIBRARY - LATEST BROCHURES
FRAMESAFE 5000 FR
By Glidevale Protect Co...
Novantica - Cement F...
By Fassa Bortolo
Fassatherm System -...
By Fassa Bortolo
Fassarend System - P...
By Fassa Bortolo
Fassalime System - P...
By Fassa Bortolo
BUILDING PRODUCT DIRECTORY - LATEST PRODUCTS
Straightcurve® – headquartered in Australia, is renowned for high-end innovative garden edging,...
The Kingspan RLG600 raised access floor panel is intended for light office use and is capable of...
Kingspan RHG600 Simploc is the heavy grade floor system, capable of handling up to a 12kN/m2...
CONSTRUCTION VIDEOS - LATEST VIDEOS
“Building with stone wool insulated sandwich panels” written by Professor Imperadori, is now...
Portakabin | Installation at the iconic Admiralty Arch, London