Regeneration Tue, Mar 22, 2016 5:06 PM
In a review of the London 2012 Games, the National Audit Office has underlined the success of the Games and stressed the importance of building on that success to deliver the promised legacy benefits.
The report to Parliament draws out some of the widely acknowledged successes of the Games. These include the widely praised opening and closing ceremonies and the 11 million tickets sold for the Olympics and Paralympics combined. LOCOG met the huge logistical challenge of recruiting and deploying 70,000 volunteers and medal targets were exceeded, with the Olympic and Paralympic teams winning 65 and 120 medals respectively.
Since London was awarded the Games in 2005, the Government’s preparations and management of the £9.3 billion Public Sector Funding Package have been led throughout by the Department for Culture, Media and Sport. According to today’s report, there is likely to be a £377 million underspend against the £9.3 billion Public Sector Funding Package, though the final position depends on the accuracy of assumptions about remaining expenditure and will not be known precisely until 2014. The final position is subject to some remaining areas of uncertainty: for example, the final cost of converting the Athletes’ Village, and of settling outstanding contracts with suppliers.
Since the Funding Package was set in 2007, the operational costs within it have increased markedly; most notably, it has had to cover £500 million additional costs for venue security, for which there was originally no provision. However, the Funding Package as a whole has been able to cover these costs. The final cost of the Olympic Delivery Authority’s programme to build the venues and associated infrastructure is expected to be around £6.7 billion, compared to the £8.1 billion that was originally available to it.
The Cabinet Office now has central responsibility for coordinating and assuring delivery of the legacy, and these new arrangements are a positive step towards maintaining focus and direction after the Games themselves. With numerous organisations responsible for particular aspects of the legacy, the Cabinet Office will need to provide strong leadership to make the most of the momentum created by the success of the Games. While the future use of the Olympic Stadium is still uncertain, most venues and facilities on the Olympic Park now have an agreed long-term use and legacy tenant.
The spending watchdog also recommends that the valuable skills in project management, contracting and risk management gained by officials who have worked on the Games be deployed on other public sector projects.
Featured News
Hatchards is a British institution. Occupying 187 Piccadilly, it is the oldest...
Following the revelation that there were 3.6 million hours of sewage spills into UK...
BUILDING PRODUCT DIRECTORY - LATEST PRODUCTS
Straightcurve® – headquartered in Australia, is renowned for high-end innovative garden edging,...
The Kingspan RLG600 raised access floor panel is intended for light office use and is capable of...
Kingspan RHG600 Simploc is the heavy grade floor system, capable of handling up to a 12kN/m2...
CONSTRUCTION VIDEOS - LATEST VIDEOS
“Building with stone wool insulated sandwich panels” written by Professor Imperadori, is now...
Portakabin | Installation at the iconic Admiralty Arch, London